Add a shift at Assembly
Adds costPredict bottlenecks before they delay production.
Trooba Flow reveals where work will queue, how lead times will change, and where hidden capacity exists — before delivery performance is affected.
Routing · projected utilisation and queue
- Milling62%queue 0.5 d
- Lathe74%queue 1.1 d
- Assembly91%queue 3.2 d
- Packing58%queue 1.4 d
Illustrative model of a four-operation plant.
Your factory may have capacity. Flow determines how much of it you can use.
Routing · projected utilisation and queue
- Milling62%queue 0.5 d
- Lathe74%queue 1.1 d
- Assembly91%queue 3.2 d
- Packing58%queue 1.4 d
Lead time by operation
Moving part of the Assembly load to a line the routing can already reach takes Assembly from 91% to 80%. Processing time does not change at all — every day saved is a day of waiting removed.
From factory data to a decision.
Every screen answers three questions in the same order: what is happening, why, and what to do about it.
- Analysis
- Overview
- Bottleneck Radar
- What-if Studio
- Flow & Queue
- Capacity
- Model
- Routings
- Resources
- Demand
What is happening
Assembly is predicted to become the next constraint.
Why
Demand mix is shifting toward products that need more Assembly time.
Work arrives from Lathe in large transfer lots, in bursts rather than steadily.
What to do
Move part of the Assembly load to a second qualified line.
- Analysis
- Overview
- Bottleneck Radar
- What-if Studio
- Flow & Queue
- Capacity
- Model
- Routings
- Resources
- Demand
What is happening
One resource crosses the review threshold in the next ten days.
Ranked on projected queue behaviour, not on utilisation alone. A resource at 81% with steady arrivals can run calmer than one at 74% receiving work in bursts.
| Resource | Projected utilisation | Projected queue |
|---|---|---|
| Assembly | 91% | 3.2 d |
| Lathe · Line 2 | 81% | 0.8 d |
| Lathe · Line 1 | 74% | 0.6 d |
| Milling | 62% | 0.3 d |
| Packing | 58% | 0.2 d |
| Slitting | 41% | 0.1 d |
- Analysis
- Overview
- Bottleneck Radar
- What-if Studio
- Flow & Queue
- Capacity
- Model
- Routings
- Resources
- Demand
What is happening
The change that costs nothing is the largest one.
Three scenarios against the same model. Moving part of the load to a line the routing can already reach takes Assembly from 91% to 80% utilisation — and buys more lead time than paying for a second shift.
Halve the transfer lot at Lathe
Adds setupsMove part of the load to a second line
No added capacitycapacity
| Scenario | Lead time | Change | Trade-off |
|---|---|---|---|
| 01 Add a shift at Assembly | 6.6 d | −21% | Adds cost |
| 02 Halve the transfer lot at Lathe | 5.9 d | −30% | Adds setups |
| 03 Move part of the load to a second line | 5.1 d | −39% | No added capacity |
- Analysis
- Overview
- Bottleneck Radar
- What-if Studio
- Flow & Queue
- Capacity
- Model
- Routings
- Resources
- Demand
What is happening
Three quarters of lead time is waiting, not work.
Lead time is decomposed operation by operation into processing, waiting and batching — so the argument is about where the time goes, not whether it is there.
- Analysis
- Overview
- Bottleneck Radar
- What-if Studio
- Flow & Queue
- Capacity
- Model
- Routings
- Resources
- Demand
What is happening
One line has capacity the routing can reach and is not using.
Before capital goes into a machine, the model shows what is already available and what would have to change — a routing, a qualification, a setup — to reach it.
Trooba Flow. Figures throughout are from an illustrative model, not a customer result.
Measured in a real factory.
28 → 7 days
>75% reduction in manufacturing lead time · same factory, same machines
The constraint was not machine speed. It was lot sizing and queue dynamics — the way work was moving through the system.
Tarinika · jewellery manufacturer ·
multi-SKU, make-to-order.
Tarinika is the founder’s
manufacturing company.
Model. Understand. Improve.
Model
Products, routings, resources, demand and variability.
Understand
See where queues, constraints and lead time emerge.
Improve
Test changes before making them on the factory floor.
Sophisticated underneath. Simple where it matters.
Trooba models how demand, variability, routing and resource loading interact to create queues and lead time. AI explains the model. The mathematics grounds it.
See how work really flows through your factory.
Share a small set of factory data and see where queues, bottlenecks and hidden capacity are affecting performance.